Line output calculator
It goes from the nominal machine speed to the containers that actually come out per hour and per shift, discounting line efficiency. Useful to check a quotation, plan shifts or verify that a nominal rate covers demand.
Line output
Theoretical and actual output from speed, efficiency and shift hours.
Actual = speed × 60 × efficiency
Pre-selection and estimation tool. Check the result against the real data of your product and manufacturer.
Formulas
- Theoretical output (containers/h) = speed (containers/min) × 60
- Real output (containers/h) = theoretical × efficiency (%) ÷ 100
- Output per shift = real × hours per shift
Worked example
A 40 containers-per-minute filler has a theoretical output of 2,400 containers/h. At 85 % efficiency, 2,040 real containers/h come out, that is 16,320 containers in an 8-hour shift. If demand is 18,000 per shift, the machine alone is not enough: efficiency or speed must go up.
Limits and how to use it
- Efficiency bundles stops, micro-stops, changeovers and rejects; if you know the three factors separately, use the OEE calculator.
- The speed must be that of the line bottleneck, not of the fastest machine.
- Hours per shift are scheduled production hours, net of breaks and start-ups if they are not already in the efficiency.
Other calculators
Written byÁngel Coronil García · Founder and Engineering Director
Industrial engineer, founder and engineering director of SOLINDAC. He designs packaging and process machinery, special-purpose machines and line automation from Villamartín (Cádiz, Spain), after years as technical director at a packaging machinery manufacturer. Professional profile →
Got a process to automate?
Tell us the product, the format and the output you need. You get a technical proposal back, not a catalogue.
Request a quote